| No |
Identified element of defective work |
Reason work is defective/brought to the Contractor's
attention |
Date brought to Contractor's attention |
Date brought to the attention of Consultants/HBG |
Action taken |
Date satisfactory action carried out |
| 130 |
Tunnelform rooms 57-60 level 2 |
Reinforcement lapped at joints when should be spliced as
per Blyth & Blyth details |
12/3/01 |
12/3/01 |
Concrete cover correct but floor cast without Blyth &
Blyth confirmation of acceptance |
22/3/01 |
| 131 |
Room 57 level 2 electrical conduit |
Conduit broken within wall |
13/3/01 |
- |
Floor above opened up at head of wall and conduit
replaced |
17/3/01 |
| 132 |
Tunnelform rooms 56-58 & 60 |
Honeycombing at conduits/back boxes and at kicker |
12/3/01
13/3/01 |
13/3/01 |
Concrete finisher repaired walls using grout whilst
green |
12/3/01 &
13/3/01 |
| 133 |
Tunnelform rooms 49 & 50 |
Soffit concrete frosted |
16/3/01 |
16/3/01 |
Concrete broken out, new frost blanket now in use |
17/3/01 |
| 134 |
Tunnelform rooms |
Release oil to shutters not working, surface of concrete
being ripped off when shutter moved |
19/3/01 |
19/3/01 |
Walls being resurfaced as required |
on-going |