Work Activities Progressing
Activity 4 - Sub Slab Drainage Sumps
No progress this week. Still awaiting details of cover slabs from
Blyth & Blyth
Activity 11 - Construct Basement Walls up to Ground Floor
Level
Completed this week
Activity 16
Scenic Lift, 1st to 2nd Floors
Completed
Scenic Lift, 2nd to 3rd Floors
In progress, 20% completed and progressing during night shift working
Activity 18 - Construct Core Areas 2nd Floor
to Roof Level
Core 1 - Completed up to 4th floor slab. No progress
this week
Core 2 - Completed up to 4th floor slab. 30% completed to 5th floor. in
progress
Core 3 - Completed up to 4th floor slab. 60% completed to 5th floor. in
progress
Core 4 - Completed up to 5th floor slab
On programme
Activity 20 - Install Bathroom Pods Level 2
All pods now landed and in rooms
12 pods now completed line and level and grouted into finish position
Work ongoing
4 weeks behind programme
Activity 21 - Construct Tunnelform Rooms Level
3
Completed this week
Activity 22 - Install Bathroom Pods Level 3
Completed this week landing pods into rooms
No start made as yet to line and level
On programme
Activity 23 - Tunnelform Rooms at 4th Floor
Level
5 rooms left to concrete to this floor. Little
progress this week with concentration on core 3 works at this position.
1 week ahead of programme
Activity 24 - Install Bathroom Pods to 4th
Floor Rooms
No progress this week
1 week ahead of programme
Activity 25 - Tunnelform Rooms Level 5
16 remaining to be completed around Cores 1 and 3
only. Good progress achieved and work to these above areas due to
commence next week
4 weeks ahead of programme
Activity 26 - Install Bathroom Pods Level 5
Hi-tech rooms, pods not in production yet
Activity 27 - Tunnelform Rooms 6th Floor Level
In progress with first 4 rooms to Robertson Street concreted successfully
this week
Installation/erection of kickers, reinforcement and conduits to walls are
advancing satisfactorily.
5 weeks ahead of programme
Activity 28 - Install Bathroom Pods to 6th
Floor
Not started yet - imminent delivery and installation
Activity 30/32 - Courtyard Roof (Deflected
Sections)
Discussed by client now and awaiting HBG proposals based upon clients
statements at progress meeting on Friday 8th June 2001
Activity 31 - Erect Pre-cast Slabs to
Courtyard Plus Topping
First section of pre-cast delivered and erected grids D-6/5-6.
Second section at Core 3 due for delivery Sunday 10th June.
Remainder still on hold pending HBG decision of courtyard.
Deflected steelwork resolution
6 weeks behind programme
Activity 33 - Construct Landings & Stairs
within Core Areas
Core 1 - In progress basement to ground floor level
Core 2 - In progress up to1st floor level and landings from 1st to 2nd
floors.
Core 3 - Not yet started
Core 4 - In progress basement to ground floor levels.
10 weeks behind programme
Activity 36 - Floor Construction to Steelwork
Rooms
Wedge Suite - Completed including roof concrete slab.
Activity 40 - Blockwork Walling
Basement - No progress
Ground floor - In progress to all areas 92% completed but still unable
to complete due to co-ordination of access holes through walls for service.
1st Floor - Secondary steelwork in progress to both Robertson Street
and Oswald Street elevations. Loading out blocks in progress
2nd floor - Loading out commenced
3rd floor - Loading out commenced
6 weeks ahead of programme
J Smith, Site Inspector
Signed on behalf of
John Arnott Associates
-------------------------------------------
Copies to:
Client
Project Manager
Architect
Engineer
J Shaw, John Arnott Associates
Office File Copy
Sample weekly
report Items
brought to Contractor's attention
Record of site delays observed
Site daily diary sheet
Site daily diary sheet page 2
|