WEEKLY REPORT
Week ending:  
Date:

Report No : 50 Inspector:  J Smith Project No: 123/45
                 
LABOUR RECORD S M T W T F S PROJECT : NEW OFFICE BLOCK
Project manager   1 1 1 1 1    
Site Engineer & Assistant 3 6 6 6 6 6 5 Plant: 2 tower cranes, JCB 33c & breaker, tunnel form shutters. mobile concrete pump, 2 compressors, forklift, 2 barrow hoists, hoist, blow heaters, bar bender, saw bench, power lift platform, poker vibrators, 2 power floats
Agent 2 5 5 5 5 5 2
General Foreman 1 3 3 2 2 2 2
Ganger 3 7 7 7 7 7 6
Labourers 2 12 12 12 12 12 10
Steelfixers 4 10 10 10 10 10 10  
Steel Erectors/Blacksmith   3 6 3 8 8 2 EAV I's to date :
Drainlayers 1 1 1 1 1 1 1 EAI's:  None
Machine Ops 1 2 2 2 2 1 1  
Joiners 6 18 18 20 21 21 18 Dayworks :
Joiner labourers                
Bricklayers   5 5 5 5 5   Days lost this week :
Bricklayer Labourers   3 3 3 3 3   Visitors:

M Barlow - GM & AD
J McGuire-Thomas & Adamson
S Bunton-JAA
A Dunlop-GM & AD
B Broadbent, B Day-MWB
A Walker-Gleeds
D Drummond-Currie & Brown
C Harrowmore-Thomas & Adamson
T Beltram-Blyth & Blyth
M Sneddon-Blyth & Blyth

Stonework-Stirling Stone              
Pump Driver   1 1 1 1 1 1
Banks men 2 3 3 3 3 3 3
Fitters              
Crane Drivers 2 4 4 4 4 4 3
Finishers   6 6 6 6 6 6
Heating/Ventilation Eng   4 4 4 6 6  
Chain boys 1 3 3 3 3 3 3
Plumbers ECG              
Electricians 5 18 18 18 17 17 13
Store men 1 2 2 2 2 2 1
Cleaners/Canteen   2 2 2 2 2 1
Scaffolders 4 11 14 14 12 12 9

TOTAL

38 132 133 134 139 138 97  

 

WEATHER REPORT C
am
Weather C
pm
Weather

Time Lost

Sunday 8 Dry 17 Dry -
Monday 8 Dry 20 Dry -
Tuesday 9 Dry 18 Dry -
Wednesday 11 Dry 18 Dry -
Thursday 10 Dry 21 Dry -
Friday 11 Dry 19 Dry -
Saturday 8 Dry 15 Dry -

 

Work Activities Progressing

Activity 4 - Sub Slab Drainage Sumps
No progress this week.  Still awaiting details of cover slabs from Blyth & Blyth

Activity 11 - Construct Basement Walls up to Ground Floor Level
Completed this week

Activity 16
Scenic Lift, 1st to 2nd Floors
Completed
Scenic Lift, 2nd to 3rd Floors
In progress, 20% completed and progressing during night shift working

Activity 18 - Construct Core Areas 2nd Floor to Roof Level
Core 1 - Completed up to 4th floor slab. No progress this week
Core 2 - Completed up to 4th floor slab.  30% completed to 5th floor. in progress
Core 3 - Completed up to 4th floor slab.  60% completed to 5th floor. in progress
Core 4 - Completed up to 5th floor slab
On programme

Activity 20 - Install Bathroom Pods Level 2
All pods now landed and in rooms
12 pods now completed line and level and grouted into finish position
Work ongoing
4 weeks behind programme

Activity 21 - Construct Tunnelform Rooms Level 3
Completed this week

Activity 22 - Install Bathroom Pods Level 3
Completed this week landing pods into rooms
No start made as yet to line and level
On programme

Activity 23 - Tunnelform Rooms at 4th Floor Level
5 rooms left to concrete to this floor.  Little progress this week with concentration on core 3 works at this position.
1 week ahead of programme

Activity 24 - Install Bathroom Pods to 4th Floor Rooms
No progress this week
1 week ahead of programme

Activity 25 - Tunnelform Rooms Level 5
16 remaining to be completed around Cores 1 and 3 only.  Good progress achieved and work to these above areas due to commence next week
4 weeks ahead of programme

Activity 26 - Install Bathroom Pods Level 5
Hi-tech rooms, pods not in production yet

Activity 27 - Tunnelform Rooms 6th Floor Level
In progress with first 4 rooms to Robertson Street concreted successfully this week
Installation/erection of kickers, reinforcement and conduits to walls are advancing satisfactorily.
5 weeks ahead of programme

Activity 28 - Install Bathroom Pods to 6th Floor
Not started yet - imminent delivery and installation

Activity 30/32 - Courtyard Roof (Deflected Sections)
Discussed by client now and awaiting HBG proposals based upon clients statements at progress meeting on Friday 8th June 2001

Activity 31 - Erect Pre-cast Slabs to Courtyard Plus Topping
First section of pre-cast delivered and erected grids D-6/5-6.
Second section at Core 3 due for delivery Sunday 10th June.
Remainder still on hold pending HBG decision of courtyard.
Deflected steelwork resolution
6 weeks behind programme

Activity 33 - Construct Landings & Stairs within Core Areas
Core 1 - In progress basement to ground floor level
Core 2 - In progress up to1st floor level and landings from 1st to 2nd floors.
Core 3 - Not yet started
Core 4 - In progress basement to ground floor levels.
10 weeks behind programme

Activity 36 - Floor Construction to Steelwork Rooms
Wedge Suite - Completed including roof concrete slab.

Activity 40 - Blockwork Walling
Basement - No progress
Ground floor - In progress to all areas 92% completed but still unable to complete due to co-ordination of access holes through walls for service.
1st Floor - Secondary steelwork in progress to both Robertson Street and Oswald Street elevations. Loading out blocks in progress
2nd floor - Loading out commenced
3rd floor - Loading out commenced
6 weeks ahead of programme

J Smith, Site Inspector
Signed on behalf of
John Arnott Associates

 

 

-------------------------------------------

Copies to:

Client
Project Manager
Architect
Engineer
J Shaw, John Arnott Associates
Office File Copy

Sample weekly report    Items brought to Contractor's attention    Record of site delays observed
Site daily diary sheet  Site daily diary sheet page 2

John Arnott Associates
Site Inspection Services
The Lodge, 
Nether Cambushinnie
Cromlix
DUNBLANE
Perthshire
FK15 9JU

tel : 01786 880882
fax : 01786 880884

e-mail : sheila@johnarnott.co.uk
e-mail : enquiries@johnarnott.co.uk